Shop Fabricated, Field Installed Evaporators

Evaporators
Up
Next

We fabricated the second through fifth Effects and Surface Condensers of a new Evaporator set for a Greenfield project at Castlegar, British Columbia. The units were fabricated in our Seattle shop. Heater sections were fabricated in 2 pieces each, the Vapor Domes in 3 pieces while the Surface Condenser was fabricated complete. The Heaters and Vapor were shipped to the site utilizing a Schnable system between two trucks. The heaviest unit was 194,000 pounds. At an off-site location, we assembled both Vapor Domes and Heaters including stuffing the Tubes. Then we moilized the main lift Crane to the site, moved the Heater and Vapor Dome assemblies to the crane and set them on the Structural Steel

 

Previous
 
PSF INDUSTRIES, INC.      

Craftsmen Serving Industry Since 1900

Welding on tank        